Construction Forecast – November 14 – 18
Work continues on the Wastewater Treatment Plant Detention Pond in Northcrest Village. Heavy equipment will be excavating and moving dirt, particularly on the east side of the property near the proposed entry road. A silt fence will be installed to help control dirt entering adjacent yards. Work is not currently scheduled for Saturday, November 19. We will update you if that changes.
Following resident reports of early work hours, we reminded the contractor that work is not to begin before 7 a.m. without prior approval. If you see crews onsite before 7, please let us know.
Thank you for your continued patience during this project.