Busy Time at Wastewater Treatment Plant 2 Site

May 19, 2023 10:07 am

There will be a noticeable increase in both construction and delivery traffic at the Wastewater Treatment Plant 2 site over the next few weeks. Crews will be working in multiple locations throughout the site. Check out the latest Construction Forecast below for more information.


Construction Forecast

June 28 – July 7

Residents may continue to see trucks entering and exiting the property, as well as construction machinery and personnel working in multiple areas of the site.

Residents may experience some excess dirt, mud, and noise as a byproduct of the ongoing construction. The contractor is actively trying to limit any impacts from this construction. Silt fencing will remain in place throughout construction to assist with the containment of the construction materials and dirt. Additional care is also being taken to ensure inlets and ditches are cleaned and kept clear of debris to maintain proper drainage.

Work is planned in the southern area of the site on June 29 and 30. There are no plans to work on the 4th of July or the weekend of July 6 and 7. We will advise if the schedule changes due to weather or safety concerns.

Dark ModeLight Mode