Construction Forecast

December 5 – December 9

The primary focus for construction this week will be the access road on the east side and the plant utility infrastructure in the center of the property. Crews will also be working along the southeast end of the property, installing piping where the pipeline easement crosses Northcrest Village Way. Construction machinery, concrete and delivery trucks will be onsite throughout the week.

No work is scheduled for Saturday, December 10. We will post an update if this changes.

November 21 – December 2

Crews will continue working to relocate dirt and raise the elevation in strategic locations on the Wastewater Treatment Plant 2 site. Residents on Beeston Hall Court, Northcrest Village Way, and Catoosa Drive will see heavy equipment in the area. The silt fencing has been installed to try and minimize the impacts of any excess dirt. Once the site elevation has reached the desired levels, we will begin pouring concrete. Mixing trucks and other delivery trucks will also be entering and exiting the site during this time.

No work is scheduled for November 24-26, in observance of the Thanksgiving Holiday. As always, our updates are subject to change, due to inclement weather.

November 14 – November 18

This week, construction will continue on the Wastewater Treatment Plant 2 Detention Pond. Crews will be focused on relocating dirt to the proposed new entry road on the east side of the road. We have been told that the contractor will be installing a silt fence to help contain dirt from the site. Concrete trucks will be on and off site through the week, pouring concrete.

We reminded the advised the contractors that work is not to begin before 7 a.m. without prior notice. No work is scheduled for Saturday, November 19th.

November 7 – November 11

Work continues on the Wastewater Treatment Plant Detention Pond in Northcrest Village. Heavy equipment will be in use as we move dirt to strategic locations and raise the elevation for construction. We do not expect the crews to be onsite on Saturday, November 12, but if conditions change, we will provide updates.

October 31 – November 4

Crews will be working in Northcrest Village this week on the Wastewater Treatment Plant Detention Pond. The excavation team will be using heavy equipment to remove dirt behind Beeston Hall Court and Catoosa Drive. The contractor is aware of residents’ concerns about excess dirt and will make every effort to minimize the impact. We do not expect the crews to be onsite on Saturday, November 5, but if conditions change, we will provide updates.